Door Design, Procurement & Installation

The challenge of doors in large operational project at London Bridge station

Doors may look simple. However when you have a complex project like the London Bridge station redevelopment with over 1100 doors in different locations, with different sizes, locking mechanisms, access control, fire rating and security requirements, the reality of doors becomes more challenging than the simple functionality like opening and closing.

This case study captures and documents the “door” experiences with the challenge of meeting several delivery milestones on the London Bridge station redevelopment project. Its purpose is to capture the processes used and lessons learned during the project delivery, for future knowledge transfer to other projects that may want to adapt these to their needs.

Case Study

Door Design, Procurement & Installation

Project: London Bridge station