Operational Readiness
Keeping London Bridge Station operational for trains and passengers throughout its transformation
Keeping London Bridge station moving
This case study looks at how the lessons learned drawn from previous major projects, alignment of the project programme, forum and governance mapping and reorganisation of the project development team all contributed towards a successful operational readiness programme at London Bridge station.
In this interview, Christine Carter, Operational Readiness Manager, talks about the sequence of actions taken by the team to be ready for London Bridge station to open for passengers.