Video: London Bridge gets ready for major Easter works

Video: London Bridge gets ready for major Easter works

 

During the Easter weekend and both May bank holidays, there will be major engineering works taking place at London Bridge Station and the surrounding area. The station’s £1bn redevelopment, is currently in its final phase ahead of completion in 2018.This will mean closures and changes to services over Easter, both May bank holidays, August and December, as Network Rail continues to rebuild London Bridge and the surrounding railway.

Andrew Hutton, Network Rail’s lead development manager for London Bridge station has been behind the hoardings as the team gears up for the upcoming works due to take place in the coming weeks.

Since January, great progress has been made on the final section of the new, street-level concourse, which will open in January 2018. The foundations are being formed for the station façade and the lifts, stairs and escalators have been installed. The team has also been busy assembling the pre-cast bridge decks that will support platforms 1, 2 and 3, and building the steelwork sections that will form the canopies above.

This is in preparation for Easter, when the orange army will be bringing into use the tracks through platforms 1 and 2 at London Bridge and carrying out track and signalling work in the surrounding area. There will be no Southeastern trains to or from Charing Cross, Waterloo East and London Bridge on Friday 14 and Saturday 15 April and no trains to or from Cannon Street between Friday 14 and Monday 17 April inclusive. There will also be no Southeastern trains at Deptford, Greenwich, Maze Hill or Westcombe Park over the four day weekend; passengers wishing to attend Tall Ships Royal Greenwich 2017 should be aware of alternative options.

Crane lifting track into place under the new platforms at London Bridge

 

 

 

 

 

 

 

 

 

 

 

 

 

Andrew Hutton, Network Rail’s lead development manager for London Bridge station said: “As the redevelopment of London Bridge by the Thameslink Programme leaps towards completion, I would like to thank passengers for their patience. We understand that it has been tough and urge passengers to plan ahead throughout 2017, while we work round-the-clock on our Railway Upgrade Plan to improve journeys to and through London for the millions of passengers that use the UK’s busiest stretch of railway each year.”

Ellie Burrows, Train Services Director at Southeastern said: “The work being done at London Bridge has been, and continues to be, hard on our passengers, but we are confident it will be worth it. The new station will improve the experience and journey for our passengers and we cannot wait for them to see the benefits in 2018. We thank our passengers for their continued patience and urge them to plan ahead and to make alternative arrangements during the planned engineering work happening during Easter and the May bank holidays, and during August and December, when working days will be significantly affected by closures.”

Passengers are advised to look ahead to August and Christmas 2017 when significant engineering work will take place at and around London Bridge, including on working days.

In August, significant work will take place over the bank holiday and the four working days after. There will be no Southeastern services at London Bridge, Waterloo East and Charing Cross for 8 days. Those trains that do run will be diverted to alternative London stations and will be extremely busy, with queuing systems in place.

There will be further big changes happening at Christmas, with no trains at a number of London stations between Saturday 23 December 2017 and Tuesday 2 January 2018. Journeys will be significantly affected and passengers are advised to look ahead and consider their plan B in advance.

More information and travel advice will be available closer to the time.